Tunnelling completes on London Power Tunnels Project

Charlotte S Charlotte Fernández UKIMEA Press Office,Leeds
30 March 2015

Major project milestone reached for National Grid’s largest single programme of works.

National Grid has completed the final section of tunnelling on its London Power Tunnels (LPT) project. The project ensures that National Grid will be able to provide the power infrastructure to enable growth in London as well as securing access to future renewable energy generation.

Arup has been involved in the project since 2009 and has provided Programme and Project Management throughout, as well as a number of specialist technical services.

The main elements of LPT are two 32km tunnels with diameters of 3m and 4m. The tunnels have been dug 60m deep, and will house two cables 180km and 60km in length. The project also includes the construction and commissioning of two new 400kV substations (one at Kensal Green and another at Highbury) and the modification of four existing substations.

We are tremendously proud to have been at the heart of one of the most important infrastructure projects in London, helping National Grid deliver the single biggest upgrade of transmission systems since they were built in the 1960s.

Mark Neller, Project Director, Arup

Additional specialist services provided by Arup included procurement support, technical innovation, tender evaluation, health and safety support, information management, environmental impact assessment, project management and leadership of other consultancies providing cost management and contract administration services.